GTU-25P Industrial Gas Turbine
Among perm gas turbines GTU-25P has got the highest power rated at 25 MW. It is intended to drive gas compressors in new-generation gas compressor packages, and to pump gas into underground gas storage.
GTU-25P is based on the PS-90GP-25 gas turbine engine, which is an industrial derivative of the high efficiency PS-90A aero engine incorporating as well GTU-12P and GTU-16P gas turbine components.
The engine consists of:
- two-shaft gas turbine gas generator module;
- power turbine module.
The engine and power turbine located on the common engine mount are installed on the gas compressor package skid.
Developer - OJSC "Aviadvigatel"
Mass Producer - OJSC "Perm Engine Company"
Primary Performance DataISO Conditions, loss-free, fuel: Methane (LHV=11958 kCal/kg)
| Power turbine shaft output, MW | 25.6 |
| Efficiency at power turbine shaft, % | 40.0 |
| Exhaust gas temperature, °Ñ | 451 |
| Output speed, rev/min | 5 000 |
| Exhaust gas flow, kg/s | 80.7 |
| Service life: -overhaul interval, hr -design life, hr | 25 000 100000 |
This gas turbine was developed and produced by Aviadvigatel OJSK within the scope of "Ural-Gazprom" comprehensive program. In November 2003 the high-time gas turbine was shipped to the Customer, Permtransgaz for GTN-25 gas pumping set reconstruction and in December the gas turbine was installed in "Igrinskaya" compressor station as part of GPA-25R-PS gas pumping unit (OJSC "Iskra").
In November 28 - 29 2006 the gas turbine successfully passed interdepartmental test.
In acceptance report "Gasprom" stated that GTU-25P gas turbine primary parameters, established during preliminary and acceptance tests, coincided with TECHNICAL SPECIFICATION requirements and the primary design and technological solutions of gas compressor station GPA-25R-PS "Ural" were at the level of the world standards.
Advantages
Our gas turbine units feature:
- high efficiency;
- low oil consumption;
- long service life;
- reliable turboexpander starting;
- low maintenance and repair cost during the entire life cycle;
- comprehensive process automation;
- easy operation and maintenance;
- completely factory-assembled; minimum cost and duration of installation and commissioning;
- good environmental parameters.
The experience of GTU-25P gas turbines operation
As of the beginning of January, 2009 KS "Igrinskaya", JSC "Gaspromtransgaschaikovsky", operates 2 GTU-25P gas turbines and one standby engine PS-90GP-25 as a part of 2 units GPA-25P-PS "URAL".
The operating time of GTU-25P gas turbines for the year 2008 is 5388 hours.
The total operating time of GTU-25P since operation start is 21211 hours.
The operating time of the high-time GTU 25P is 12 160 hours.
Please, see our REFERENCE LIST for more detailed field data.
Information request
If the products are of interest to you, please fill in the questionnaire.
Contact
93, Komsomolski prospect, Perm, 614990, Russia.
Mikhail A. Ignatiev
Perm Engine Company
Deputy Commercial Director-
Director Industrial Gas Turbines Program
Tel: +7 (342) 2409-444
Fax: +7 (342) 240-92-47
E-mail: mai@jetmotors.perm.ru
Mikhail F. Kharulin
Aviadvigatel
Deputy General Designer-
Chief Designer
Òål.: (342) 245-83-89
Fax: (342) 245-97-77
E-mail: office@avid.ru
Andrei L. Polyanin
Aviadvigatel
Head of the Leading dept.
Òål.: (342) 245-02-94
Fax: (342) 245-97-77
E-mail: shelkov@avid.ru
Konstantin V. Mikhaliov
Perm Engine Company
Head of Marketing dept.
Industrial GTU
Tel.: +7 (342) 240-91-94
Fax: +7 (342) 240-92-34
E-mail: mih-kv@pmz.ru